Time and materials (T&M) change orders: what you should see on the invoice
What a T&M ticket or sheet must show, who signs it, and how daily records roll up into a T&M invoice or change order, with a worked example.
What "time and materials" means
Time-and-materials (T&M) pricing pays for work by the hour plus the cost of what was used, instead of a price fixed in advance. The federal definition is a useful reference point: under FAR 16.601, a time-and-materials contract pays for direct labor hours at specified fixed hourly rates "that include wages, overhead, general and administrative expenses, and profit," plus the actual cost of materials.
Public agencies often call the same idea force account. Washington State's Standard Specifications, section 1-09.6, say the objective is to reimburse the contractor for all costs of the work, including labor, equipment, materials and overhead, with a profit commensurate with those costs.
Federal rules treat T&M as the exception. FAR 16.601 allows it only when the extent or duration of the work cannot be estimated accurately at the start, and notes that it gives the contractor "no positive profit incentive" for cost control. The federal-aid highway rule, 23 CFR 635.120, says force account procedures "shall only be used when strictly necessary," such as when the parties cannot agree on a price or the extent of the work is unknown.
Your contract is not a federal or highway contract, so these rules do not apply to it directly. They are cited here because they are public, specific, and show what a well-documented T&M charge looks like.
T&M tickets, T&M sheets and T&M invoices
This guide uses three terms:
- A T&M ticket or T&M sheet is the daily record: who worked, for how long, with what equipment, and which materials went into the work that day.
- A T&M invoice is the bill built from those daily records for a billing period.
- A T&M change order is the contract change that authorizes extra work to be paid this way.
The daily record is the part everything else depends on. Under the federal payment clause, FAR 52.232-7, a T&M contractor substantiates each payment request with evidence of actual payment and with "individual daily job timekeeping records" or other substantiation the contracting officer approves. Washington's Construction Manual tells its engineers that "accurate daily time records should always be kept when performing force account work."
What a T&M ticket should show
Drawing on those two sources, a daily ticket you can check later shows:
- The date and the extra work it belongs to.
- Labor: each worker or work classification, with regular and overtime hours. Washington requires the contractor to submit a labor list, with regular and overtime rates for every employee or work classification, before force account work begins.
- Equipment: each piece used and its hours.
- Materials: types and quantities used that day.
- Signatures (see below).
Prices do not have to be on the ticket. The ticket fixes the quantities; rates and invoices are applied afterwards.
Who signs a T&M ticket
Washington's Construction Manual recommends that the daily record "be signed by both the Inspector and a representative of the Contractor agreeing on the materials used and the hours noted for labor and equipment," and requires that the contractor receive a copy.
If your job has no inspector, the practical equivalent is for the owner or the owner's representative to sign with the contractor's foreman, each keeping a copy. In Washington's wording the signatures agree on materials and hours. Whether a signature on your job also accepts a price depends on your contract.
How tickets roll up into a T&M invoice
The invoice should be the tickets, priced:
- Labor. Hours from the tickets multiplied by the agreed hourly rates.
- Materials. Washington reimburses "invoice cost" and requires the contractor to "attach valid copies of vendor invoices"; for materials taken from the contractor's own stock, the contractor certifies the cost by affidavit.
- Equipment. Hours from the tickets at the agreed equipment rates. Washington takes its rates from a published rental rate guide.
- Markup. Applied the way the contract says, and only once.
Markup is where the two reference models differ. In the federal model the hourly rate already includes overhead and profit; with narrow exceptions the government "will not pay profit or fee to the prime Contractor on materials"; and indirect costs may be added to materials only when they are "clearly excluded from the hourly rate" (FAR 52.232-7). In Washington's model, labor is reimbursed at cost and a stated percentage is then added for overhead and profit: 29 percent on labor and 21 percent on materials in the 2027 Standard Specifications, with a separate sliding markup of 12, 10 or 7 percent on subcontractor work. Those are one agency's contract terms, not a benchmark for private work.
Either structure can be fair. Paying a rate that already includes overhead and profit and then a percentage on top of it is paying twice.
A worked example
The numbers below are hypothetical and chosen for easy arithmetic. They are not benchmarks.
| Item | From the tickets | Rate | Amount |
|---|---|---|---|
| Carpenter | 16 hours over 2 days | $85.00 per hour (includes overhead and profit) | $1,360.00 |
| Helper | 16 hours over 2 days | $55.00 per hour (includes overhead and profit) | $880.00 |
| Materials | 3 supplier invoices | At invoice cost | $612.40 |
| Equipment | Lift, 2 days | $90.00 per day | $180.00 |
| Markup on materials | Per the contract, 15% of $612.40 | $91.86 | |
| T&M invoice total | $3,124.26 |
In this example the contract sets hourly rates that already include overhead and profit, so no percentage is added to labor. The 15 percent on materials is the hypothetical contract's term. Every figure traces to a ticket, a rate in the contract, or a supplier invoice.
Ceilings and converting to a fixed price
A federal T&M contract must include "a ceiling price that the contractor exceeds at its own risk" (FAR 16.601), and the contractor has to warn the government when costs are expected to pass 85 percent of that ceiling (FAR 52.232-7). A not-to-exceed amount written into a private T&M change order does the same job.
Once the work is understood, T&M can be turned into a fixed price. Washington's specification allows force account items to be converted to agreed unit prices or lump sums at any time by agreement, and its manual calls that conversion "highly desirable."
Checklist before you pay a T&M invoice
- A signed ticket exists for every day billed.
- Hours on the invoice equal the hours on the tickets.
- Each labor rate is the rate in the contract or change order, and you know whether it already includes overhead and profit.
- Every material charge has a supplier invoice or receipt, and the quantities match the tickets.
- Equipment hours match the tickets, at the agreed rate.
- Markup is applied to the subtotals the contract names, once.
- The running total is within any not-to-exceed amount.
Common mistakes
- Signing tickets weeks later from memory instead of daily.
- Accepting an invoice with totals but no tickets behind it.
- Paying a percentage for overhead and profit on labor rates that already include it.
- Paying for materials with no supplier invoice.
- Leaving T&M open-ended after the scope is clear enough to price.
Questions people ask
What is a time and material ticket? The daily record of labor hours, equipment hours and materials used on T&M work, signed by both sides.
What should a T&M sheet include? The date, the work it covers, hours by worker or classification, equipment hours, materials and quantities, and signatures.
What should a T&M invoice include? The priced tickets for the period: labor at the agreed rates, materials with supplier invoices, equipment, and markup shown against the subtotal it applies to.
Do I have to accept T&M? That depends on your contract. This guide is informational, not a professional estimate or legal advice.
If you have a T&M invoice or T&M backup in hand, compare it against the labor and materials breakdown checklist, or read how to ask for a breakdown of a lump sum change order.