Material markup in construction: what published contracts allow and what receipts show

What a material line should show, what public contracts add on top of invoice cost, and how receipts, discounts and waste change the number.
By Change Order Check research team · Published 2026-02-10 · Updated 2026-10-05

What a material line should show

A material charge can be checked when it shows three things: the quantity, the unit cost, and how markup is treated. The General Services Administration's Equitable Adjustments clause asks for material cost "broken down by trade, supplier, material description, quantity of material units, and unit cost," with delivery either included in the unit cost or itemized.

When only a blended total is shown, you cannot tell material cost from markup.

What published contracts add to material cost

No public source establishes one normal material markup for private work. What is published is what some public owners pay on top of material cost when they pay for extra work at cost:

Contract terms Material cost is Added on top
Washington State DOT, Standard Specifications 1-09.6 Invoice cost, including "freight and handling charges and applicable taxes" 21 percent, covering overhead, profit, bonding, insurance and state business tax
California DOT, Standard Specifications 9-1.04 Purchase price including delivery, with supplier discounts subtracted 15 percent (10 percent for the contractor's own work on contracts with a time-related overhead bid item)
Federal time-and-materials contracts, FAR 16.601 and 52.232-7 Actual cost, which may include allocable indirect costs that are "clearly excluded from the hourly rate" Indirect costs as above; no profit or fee to the prime contractor on materials, except for certain transfers between affiliated companies

These are each owner's contract terms for its own projects. They are not a market benchmark, and they do not apply to a private job unless your contract adopts them. They do show two things worth copying: the markup is a stated percentage, and it is applied to a cost that can be proved.

What receipts can tell you

Washington reimburses "invoice cost" and requires the contractor to "attach valid copies of vendor invoices"; for material taken from the contractor's own stock, the contractor certifies the cost by affidavit. The engineer may also require "multiple quotations" before the work starts.

Discounts matter as well. California subtracts supplier discounts "whether you took them or not." The federal cost principles require a contractor to adjust material cost for "available trade discounts, refunds, rebates, allowances, and cash discounts" and for credits for "material returned to vendors" (FAR 31.205-26).

For a private change order, that suggests three requests: the supplier quote or invoice, the price actually paid after discounts, and a credit for anything returned.

Waste and overage

Ordering more than the measured quantity is normal for materials that are cut or can break. The federal cost principles allow for it: in computing material costs a contractor "shall consider reasonable overruns, spoilage, or defective work." The word that matters is reasonable. Ask for the waste percentage item by item, so that it is visible instead of hidden in the quantity.

Receipt review: what to look for

SignalWhy it mattersFollow-up
No supplier quote or invoiceThere is no cost basis to checkAsk for the quote or invoice
Markup applied to a subtotal that already includes markupThe percentage is counted twiceAsk for the subtotal before markup
A round-number material totalIt may be an estimate, not a countAsk for quantity times unit price
Waste factor not statedQuantity may be higher than installedAsk for the waste percentage by item
A different product than specifiedPrice and quality both changeAsk for the approved substitution

Questions people ask

Is a 20 percent markup on materials normal? No public source establishes one normal figure for private work. For comparison, Washington's 21 percent and California's 15 percent are what those agencies pay on force account work, and Washington's figure also covers bonding, insurance and tax.

Can a contractor mark up materials at all? On a private job that depends on your contract. Of the public examples above, two add a percentage. The federal time-and-materials clause lets the contractor recover indirect costs on materials but, with limited exceptions, pays no profit on them.

What should I ask for first? The supplier basis, the quantity math and the subtotal the markup is applied to.

Related: typical change order markup in published contract terms and how to check overhead and profit on your own change order. This guide is informational. It is not a professional estimate or legal advice.