Change order cost breakdown: labor and materials

A checklist for requesting a complete labor and material breakdown, so you never approve a total you can’t trace.

A fair change order shows how its total is built. If the labor or material assumptions aren’t visible, ask for the breakdown first and talk about price second.

Labor: what the breakdown should show

  • The crew role on each line (journeyman, foreman, helper, and so on).
  • Hours for each role, and the total hours billed.
  • The hourly rate, and any overtime assumptions.
  • Supervision or project-management time listed separately from trade labor.

Materials: what the breakdown should show

  • Quantity, unit, and unit price for every material line.
  • A supplier quote or invoice reference, when there is one.
  • The waste factor and any handling charges.
  • What the markup percentage is applied to.

Asking for a breakdown isn’t confrontational. It’s the normal way to confirm scope, pricing, and markup before signing off.