Change Order Check Upload estimate
Guides · guide

“Lump sum” change orders: how to ask for a cost breakdown without starting a fight

What to request behind a lump-sum change order, the breakdown public owners require, an email script, and what to do if your contractor refuses.
By Change Order Check research team · Published 2026-01-15 · Updated 2026-10-05

Why a lump sum is hard to check

A lump sum is one price for a piece of work. It is a normal way to price a change: Washington State's highway specification lets the parties convert force account (time-and-materials) items to agreed lump sums "at any time" (Standard Specifications 1-09.6).

The difficulty is that a single number shows no labor hours, no quantities and no markup, so there is nothing to compare. If you need to approve quickly, ask for structure, not justification. A short, factual request is easier to answer than an argument about the total.

What public owners require behind a lump sum

Public owners do not accept a bare number for a change. Their contracts say what has to sit behind it:

  • The U.S. General Services Administration's Equitable Adjustments clause requires "a detailed breakdown" of direct costs, markups and any change to the completion time. Materials are broken down by "quantity of material units, and unit cost"; labor by trade, occupation, "quantity of labor hours, and burdened hourly labor rate"; and each firm proposes its overhead rate and profit rate.
  • The Department of Veterans Affairs' changes clause requires "an itemized breakdown" that includes "materials, quantities, unit prices, labor costs (separated into trades), construction equipment," with labor "identified with specific material placed or operation performed."
  • On federal-aid highway projects, the state must "perform and adequately document a cost analysis of each negotiated contract change" (23 CFR 635.120).

They are the terms of public contracts, quoted because they are published and specific. They do not apply to a private job unless your contract says so. What they show is that asking for a breakdown is ordinary practice, not an accusation.

Minimum breakdown to request

CategoryWhat to requestWhy it matters
LaborHours by trade and the hourly rateLets you compare the rate with local ranges
MaterialsQuantity, unit and unit priceLets you check quantities and prices one item at a time
EquipmentWhat it is, how long, and the rateTies the charge to a specific operation
MarkupPercentage and the subtotal it applies toShows whether overhead and profit is applied once
ExclusionsWhat is not includedPrevents a second charge for the same work later

What a home improvement change order has to state

State law may set a minimum for homeowners. In California, for example, the notice required in a home improvement contract says a change order "is not enforceable against a buyer" unless it identifies, in writing and before the work starts, the "scope of work encompassed by the order," the "amount to be added or subtracted from the contract" and the effect on "the progress payments or the completion date" (Business and Professions Code 7159). The same section adds that a contractor who misses these requirements may still recover payment for work performed under other legal remedies.

That is California's rule. Other states differ, and none of this requires an itemized breakdown. The breakdown is something you ask for.

An email that keeps the tone cooperative

Thanks for moving quickly on this. Before I approve it, could you send a short breakdown by labor, materials, equipment and markup, with hours, quantities and rates? I want to keep the project moving and make sure we both have the same cost basis in writing.

This asks for documents the contractor already needed to produce the price.

If the contractor will not break it down

  • Ask for less: labor hours and a materials list are often enough to check the largest part of the price.
  • Offer a different pricing method for that item: time and materials with a not-to-exceed amount and daily tickets.
  • Keep the request and the answer in writing. The Federal Trade Commission's advice for a home improvement problem starts with "First try to resolve it with the contractor," and includes "Keep notes and copies of letters and documents for your files" (FTC).

If you already have a breakdown, compare it against the labor and materials breakdown checklist or work through the 12 questions to ask about price and markup. This guide is informational. It is not a professional estimate or legal advice.

Have the estimate or change order in hand?

Upload it and see which lines are worth questioning. The preview is free; $19 only if you keep the full report.

Upload your change order