Change Order Check Upload estimate
Guides · guide

Typical change order markup (OH&P): what public contracts allow

There is no single typical overhead and profit markup. See the change order markup that federal and state contracts publish, and what each percentage covers.
By Change Order Check research team · Published 2025-12-01 · Updated 2026-10-05

People search for a typical change order markup hoping for one number. No public source establishes one typical figure for private construction, and the terms that public owners publish vary, as the table below shows. So this guide does not offer a single number. It sets out what public owners write into their own contracts: the overhead and profit (OH&P) they will pay on a change, the cost it is applied to, and what it has to cover.

Each figure below is that agency's contract term for its own projects. None is a market benchmark, and none applies to a private job unless your contract adopts it. They are useful because they are published, specific, and show how a markup is built.

What overhead and profit cover

Overhead is the cost of running the job and the company that is not tied to one task. Profit is what is left for the contractor after costs. Public contracts spell out what their percentages include, and the lists differ:

  • The Department of Veterans Affairs says its overhead and fee percentages include "field and office supervisors and assistants, security police, use of small tools, incidental job burdens, and general home office expenses," with no separate allowance for them (48 CFR 852.243-70).
  • Washington State's highway specification says its percentage on labor covers "project overhead, general company overhead, profit, bonding, insurance" and state business tax (Standard Specifications 1-09.6).
  • California's highway specification says its labor markup pays for home office overhead, field office overhead, bond costs, profit, labor liability insurance and other fixed or administrative costs (Standard Specifications 9-1.04).

Two percentages can only be compared when they cover the same things.

Published change order markup allowances

Contract terms Scope Overhead and profit allowed
U.S. Department of Veterans Affairs, 48 CFR 852.243-70 VA construction contracts; changes of $500,000 or less Not more than 10% overhead and 10% profit on the first $20,000; 7.5% and 7.5% on the next $30,000; 5% and 5% on the balance over $50,000
U.S. General Services Administration, GSAR 552.243-71 GSA construction contracts Overhead rate negotiated; profit negotiated, not over 10% "unless entitlement to a higher rate of profit may be demonstrated"
Washington State DOT, Standard Specifications 1-09.6 State highway contracts; work paid by force account 29% on labor cost; 21% on materials; 21% on equipment
California DOT, Standard Specifications 9-1.04 State highway contracts; change order work paid at force account 35% on labor cost; 15% on materials; 15% on equipment rental. On contracts with a time-related overhead bid item, the contractor's own work gets 30%, 10% and 10% instead

The first two rows set limits for a negotiated price. The last two apply to force account work, where the agency pays actual cost plus a fixed percentage. Washington's percentages state that they cover bonding and insurance; California's labor markup lists bond costs among its contents.

The base matters as much as the percentage

A percentage means nothing until you know what it multiplies.

  • VA: the allowances are "based on the value of labor, material, and equipment required to accomplish the change," and profit is computed "by multiplying the profit percentage by the sum of the direct costs and computed overhead costs." Ten percent overhead and 10 percent profit therefore come to 21 percent of direct cost, not 20.
  • GSA: overhead is applied to "the direct costs of work performed by a firm," and profit to "the sum of a firm's direct costs and the overhead allowed" on them.
  • Washington and California: labor carries a higher percentage than materials and equipment, and the labor cost it applies to already includes payroll taxes, insurance and benefits.

Markup on subcontractor work

This is where markup stacks, and each contract limits it differently:

  • GSA: a contractor gets no "overhead or profit on the overhead or profit received by a subcontractor." On a subcontractor's direct costs it may add half of its own negotiated rates, "not in excess of ten percent when combined."
  • VA: the same declining scale sets the prime contractor's fee on subcontracted work, "to a maximum of three tiers," based on "the net increased cost."
  • Washington: when an approved subcontractor does the work on a force account basis, 12 percent on amounts up to $50,000, 10 percent between $50,000 and $200,000, and 7 percent at $200,000 or more, calculated for each subcontractor.
  • California: "an additional 10 percent markup" on subcontracted force account work, "as reimbursement for additional administrative costs."

Bond and insurance

GSA lets a contractor propose a separate bond rate and insurance rate. When they are a percentage of the change in contract value, they are "applied after all overhead and profit is applied," and they are not allowed at all "if the associated costs are included in the calculation of a firm's overhead rate." Washington's percentages and California's labor markup already include bond costs, and the VA percentages include "insurance other than mentioned herein."

Credits and deductive changes

The VA clause addresses work that is removed. Where a change has both added and credit items, the credits "must be deducted prior to adding overhead and profit." Where a change is a credit only, "a reasonable allowance for overhead and profit are properly includable as part of the downward adjustment," and the amount "is subject to negotiation."

A worked example

The direct costs here are hypothetical. The percentages are the agencies' published terms.

Take a change with $10,000 of direct cost, $6,000 of it labor and $4,000 materials.

VA maximum (negotiated change) Washington DOT (force account)
Direct cost $10,000.00 $10,000.00
Overhead 10% of $10,000 = $1,000.00 included below
Profit 10% of $11,000 = $1,100.00 included below
Percentage on labor 29% of $6,000 = $1,740.00
Percentage on materials 21% of $4,000 = $840.00
Total $12,100.00 $12,580.00
Markup as a share of direct cost 21.0% 25.8%

The two totals are not directly comparable, because the percentages cover different lists of costs: Washington's names bonding, insurance and state business tax, and the VA's names insurance, supervision, small tools and home office expenses. The example shows why "what is the markup?" needs three answers: the percentage, the base, and the contents.

Using this on a private change order

  • Read the markup clause in your own contract first. It controls.
  • If the contract is silent, published terms are examples of structure, not what you are owed.
  • Ask what the percentage covers before comparing it with any other number.
  • Ask what subtotal it is applied to.
  • Ask how subcontractor work is marked up, and at how many levels.

Common mistakes

  • Quoting a public agency's percentage as "the industry standard."
  • Comparing a percentage that includes bonding and insurance with one that does not.
  • Adding overhead and profit percentages together when profit is applied on top of overhead.
  • Ignoring the declining scale: the VA maximum on a large change is lower than on a small one.

Questions people ask

Is 15% overhead and profit typical? No public source establishes one typical figure for private work, and published contract terms vary. As reference points, a combined 15 percent is below the VA maximum for a small change (10 percent overhead and 10 percent profit) and below Washington's force account percentages. Each of those covers its own list of costs. Whether 15 percent is fair on your job depends on your contract and on what the 15 percent is applied to.

Is 10% overhead and 5% profit different from 15%? Slightly. If profit is applied to cost plus overhead, as the VA and GSA clauses specify, 10 percent and 5 percent compound to 15.5 percent of direct cost. On $10,000 that is $1,550 against $1,500.

Is it common to credit back overhead and profit on deductive change orders? None of the public sources used here says how common it is in private contracts. The VA clause treats a reasonable allowance for overhead and profit as part of the credit, subject to negotiation. Check what your contract says about deleted work.

How Change Order Check uses markup ranges

Change Order Check's report compares the markup on a change order with a reference range for the project type. Those ranges are set by Change Order Check from secondary industry references. They are not a survey of private contracts, they are not localized, and they are not the public contract terms listed in this guide. The methodology page says the same.

To check the markup on a change order you have in hand, use the step-by-step guide to judging overhead and profit on your own change order, the markup check, or upload the document. This guide is informational. It is not a professional estimate or legal advice.

Have the estimate or change order in hand?

Upload it and see which lines are worth questioning. The preview is free; $19 only if you keep the full report.

Upload your change order